Kitchen: Before & After Photos

I've finally finished the backsplash, except for the grout, but hey, the project is 95% done, so it's time to move on to something that's 0% done.

So let's compare the almost final product. Before:



After:



Total price tag for this minor facelift, including the carpenter, plumber, dishwasher, disposal, fridge, sink, faucet, tile, tile polishing, new knobs was a little under $4500. Time that this project took me, including shopping for materials (from appliances and fixtures to tile and grout), tiling the counter, grouting, attaching new knobs & pulls, and coordinating carpenter & plumber = 45 hours. How DO those Fix-n-Flip people do it???